700 |
How can I change the shape of the task bar
EXG2ANTTLib.Bar var_Bar = axG2antt1.Chart.Bars.Copy("Task","T2"); var_Bar.StartShape = EXG2ANTTLib.ShapeCornerEnum.exShapeIconDown1; var_Bar.StartColor = (uint)ColorTranslator.ToWin32(Color.FromArgb(255,0,0)); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Columns.Add("Column"); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Item 1"),"T2",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); var_Items.AddBar(var_Items.AddItem("Item 2"),"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); |
699 |
How can I change the starting shape for all task bars
EXG2ANTTLib.Bar var_Bar = axG2antt1.Chart.Bars["Task"]; var_Bar.StartShape = EXG2ANTTLib.ShapeCornerEnum.exShapeIconUp1; var_Bar.StartColor = (uint)ColorTranslator.ToWin32(Color.FromArgb(255,0,0)); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Columns.Add("Column"); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Item 1"),"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); |
698 |
How can I change the height of the task bar
axG2antt1.Chart.Bars.Copy("Task","T2").Height = 17; axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Columns.Add("Column"); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Item 1"),"T2",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); var_Items.AddBar(var_Items.AddItem("Item 2"),"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); |
697 |
How can I change the height for all task bars
axG2antt1.Chart.Bars["Task"].Height = 17; axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Columns.Add("Column"); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Item 1"),"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); |
696 |
How can I change the color of the task bar
axG2antt1.Chart.Bars.Copy("Task","T2").Color = (uint)ColorTranslator.ToWin32(Color.FromArgb(255,0,0)); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Columns.Add("Column"); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Item 1"),"T2",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); var_Items.AddBar(var_Items.AddItem("Item 2"),"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); |
695 |
How can I change the color for all task bars
axG2antt1.Chart.Bars["Task"].Color = (uint)ColorTranslator.ToWin32(Color.FromArgb(255,0,0)); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Columns.Add("Column"); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Item 1"),"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); |
694 |
How can I change the shape for all task bars
axG2antt1.Chart.Bars["Task"].Shape = EXG2ANTTLib.ShapeBarEnum.exShapeSolidDown; axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Columns.Add("Column"); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Item 1"),"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); |
693 |
How can I change the shape of the task bar
axG2antt1.Chart.Bars.Copy("Task","T2").Shape = EXG2ANTTLib.ShapeBarEnum.exShapeThinCenter; axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Columns.Add("Column"); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Item 1"),"T2",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); |
692 |
How can I change the pattern or style for all task bars
axG2antt1.Chart.Bars["Task"].Pattern = EXG2ANTTLib.PatternEnum.exPatternFDiagonal; axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Columns.Add("Column"); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Item 1"),"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); |
691 |
How can I change the pattern of the task bar
axG2antt1.Chart.Bars.Copy("Task","T2").Pattern = EXG2ANTTLib.PatternEnum.exPatternFDiagonal; axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Columns.Add("Column"); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Item 1"),"T2",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); |
690 |
How can I add a percent bar in the chart area, so the task bar is splited for non working days or hours
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.Bars.Add("Task%Progress:Split").Shortcut = "TS"; axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"TS",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/16/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"P1",null); var_Items.set_ItemBar(h,"P1",EXG2ANTTLib.ItemBarPropertyEnum.exBarPercent,0.14); var_Items.set_ItemBar(h,"P1",EXG2ANTTLib.ItemBarPropertyEnum.exBarShowPercentCaption,true); |
689 |
How can I add a bar in the chart area, so the task bar is splited for non working days or hours
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.Bars.Add("Task:Split").Shortcut = "TS"; axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Task 1"),"TS",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/16/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); |
688 |
How can I add a split bar in the chart area
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Task 1"),"Split",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); |
687 |
How can I add a progress bar in the chart area
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Task 1"),"Progress",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); |
686 |
How can I add a milestone bar in the chart area
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Task 1"),"Milestone",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); |
685 |
How can I add a summary bar in the chart area
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Task 1"),"Summary",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); |
684 |
How can I add a project summary bar in the chart area
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Task 1"),"Project Summary",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); |
683 |
How can I add a deadline bar in the chart area
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Task 1"),"Deadline",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); |
682 |
How can I add a task bar in the chart area
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Task 1"),"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); |
681 |
How can I assign a picture or an icon to a bar in the chart
axG2antt1.set_HTMLPicture("p1","c:\\exontrol\\images\\zipdisk.gif"); axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.set_ItemHeight(h,48); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarCaption,"<img>p1</img>"); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarHAlignCaption,2); |
680 |
How can I assign a picture or an icon to a bar in the chart
axG2antt1.Images("gBJJgBAIDAAGAAEAAQhYAf8Pf4hh0QihCJo2AEZjQAjEZFEaIEaEEaAIAkcbk0olUrlktl0vmExmUzmk1m03nE5nU7nk9n0/oFBoVDolFo1HpFJpVLplNp1PqFRqVTq" + "lVq1XrFZrVbrldr1fsFhsVjslls1ntFptVrtltt1vuFxuVzul1u13vF5vV7vl9v1/wGBwWDwmFw2HxGJxWLxmNx0xiFdyOTh8Tf9ZymXx+QytcyNgz8r0OblWjyWds+m" + "0ka1Vf1ta1+r1mos2xrG2xeZ0+a0W0qOx3GO4NV3WeyvD2XJ5XL5nN51aiw+lfSj0gkUkAEllHanHI5j/cHg8EZf7w8vl8j4f/qfEZeB09/vjLAB30+kZQAP/P5/H6/y" + "NAOAEAwCjMBwFAEDwJBMDwLBYAP2/8Hv8/gAGAD8LQs9w/nhDY/oygIA="); axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarCaption,"<img>1</img>"); |
679 |
How can I display or add an anchor or a hyperlink in the link
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/3/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.AddItem(""); var_Items.AddItem(""); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.set_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkText,"just <a1>link</a>"); |
678 |
How can I display a picture or an icon on the link
axG2antt1.Images("gBJJgBAIDAAGAAEAAQhYAf8Pf4hh0QihCJo2AEZjQAjEZFEaIEaEEaAIAkcbk0olUrlktl0vmExmUzmk1m03nE5nU7nk9n0/oFBoVDolFo1HpFJpVLplNp1PqFRqVTq" + "lVq1XrFZrVbrldr1fsFhsVjslls1ntFptVrtltt1vuFxuVzul1u13vF5vV7vl9v1/wGBwWDwmFw2HxGJxWLxmNx0xiFdyOTh8Tf9ZymXx+QytcyNgz8r0OblWjyWds+m" + "0ka1Vf1ta1+r1mos2xrG2xeZ0+a0W0qOx3GO4NV3WeyvD2XJ5XL5nN51aiw+lfSj0gkUkAEllHanHI5j/cHg8EZf7w8vl8j4f/qfEZeB09/vjLAB30+kZQAP/P5/H6/y" + "NAOAEAwCjMBwFAEDwJBMDwLBYAP2/8Hv8/gAGAD8LQs9w/nhDY/oygIA="); axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/3/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.AddItem(""); var_Items.AddItem(""); var_Items.AddItem(""); var_Items.AddItem(""); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.set_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkText,"just <img>1</img> link"); |
677 |
How can I display a picture or an icon on the link
axG2antt1.set_HTMLPicture("pic1","c:\\exontrol\\images\\zipdisk.gif"); axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/3/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.AddItem(""); var_Items.AddItem(""); var_Items.AddItem(""); var_Items.AddItem(""); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.set_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkText,"<img>pic1</img><br><br>just a link"); |
676 |
How can I display some HTML text or caption on link
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/3/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.set_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkText,"L<b>1</b>"); |
675 |
How can I assign a tooltip to a link
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/3/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.set_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkText,"L<b>1</b>"); var_Items.set_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkToolTip,"This is a bit of text that's shown when the cursor hovers the link"); |
674 |
Can I change the width or the size of the link
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.set_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkStyle,0); var_Items.set_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkWidth,2); |
673 |
Can I change the style of the link
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.set_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkStyle,4); |
672 |
Can I change the color of the link
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.set_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkColor,255); |
671 |
Can I change the part of the bar where the link ends
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.set_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkStartPos,1); var_Items.set_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkEndPos,1); |
670 |
Can I change the part of the bar where the link starts
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.set_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkStartPos,0); |
669 |
How can I associate an extra data to a link
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.set_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkUserData,"your data"); |
668 |
How can I show or hide a specified link
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.set_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkEndBar,false); |
667 |
How can I get the key of the bar where the link end
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.AddItem(var_Items.get_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkEndBar)); |
666 |
How can I get the key of the bar where the link starts
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.AddItem(var_Items.get_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkStartBar)); |
665 |
How can I get the handle of the item where the link ends
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.AddItem(var_Items.get_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkEndItem)); |
664 |
How can I get the handle of the item where the link starts
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.AddItem(var_Items.get_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkStartItem)); |
663 |
How can I enumerate the links in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.AddLink("L2",h2,"K2",h1,"K1"); var_Items.AddItem(var_Items.FirstLink); var_Items.AddItem(var_Items.get_NextLink(var_Items.FirstLink)); |
662 |
How can I access the properties and method of the link between two bars
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/3/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.set_Link("L1",EXG2ANTTLib.LinkPropertyEnum.exLinkText,"L<b>1</b>"); |
661 |
How can I remove a link between two bars
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.ClearLinks(); |
660 |
How can I remove a link between two bars
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); var_Items.RemoveLink("L1"); |
659 |
How do I add a link between two bars
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.AddLink("L1",h1,"K1",h2,"K2"); |
658 |
How do I ungroup the bars in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.GroupBars(h1,"K1",true,h2,"K2",true,null,null); var_Items.GroupBars(h1,"K1",false,h2,"K2",false,null,null); var_Items.UngroupBars(h1,"K1",h2,"K2"); |
657 |
How do I group one or more bars in the chart, so they are moved together
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h1 = var_Items.AddItem("Task 1"); var_Items.AddBar(h1,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); int h2 = var_Items.AddItem("Task 2"); var_Items.AddBar(h2,"Task",Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/7/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.GroupBars(h1,"K1",true,h2,"K2",true,null,null); var_Items.GroupBars(h1,"K1",false,h2,"K2",false,null,null); |
656 |
How do I find the number or count of bars in the item
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.set_ItemBar(h,"K2",EXG2ANTTLib.ItemBarPropertyEnum.exBarCaption,var_Items.get_ItemBar(h,"<*>",EXG2ANTTLib.ItemBarPropertyEnum.exBarsCount)); |
655 |
How can I assign any extra data to a bar in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarData,"your data"); |
654 |
How can I enable or disable resizing the percent value of a progress bar, at runtime
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Chart.Bars.Add("Task%Progress").Shortcut = "Percent"; EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Percent",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarPercent,0.35); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarCanResizePercent,false); |
653 |
Is there any way to change the background color for percent value being displayed on the progress bar
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Chart.Bars.Add("Task%Progress").Shortcut = "Percent"; EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Percent",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarPercent,0.35); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarShowPercentCaption,true); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarPercentCaptionFormat,"<bgcolor=FF0000> %p%</bgcolor>"); |
652 |
Is there any way to change the color for percent value being displayed on the progress bar
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Chart.Bars.Add("Task%Progress").Shortcut = "Percent"; EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Percent",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarPercent,0.35); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarShowPercentCaption,true); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarPercentCaptionFormat,"<fgcolor=FF0000>%p%</fgcolor>"); |
651 |
Is there any way to change the font for percent value being displayed on the progress bar
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Chart.Bars.Add("Task%Progress").Shortcut = "Percent"; EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Percent",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarPercent,0.35); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarShowPercentCaption,true); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarPercentCaptionFormat,"<b><font Tahoma;12>%%p</font></b>"); |
650 |
How can I horizontally align the caption / percent of a progress-bar
axG2antt1.BeginUpdate(); axG2antt1.Columns.Add("Task"); EXG2ANTTLib.Chart var_Chart = axG2antt1.Chart; var_Chart.LevelCount = 2; var_Chart.set_PaneWidth(false,128); var_Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Bar var_Bar = var_Chart.Bars.Add("Task%Progress"); var_Bar.Shortcut = "Percent"; var_Bar.set_Def(EXG2ANTTLib.ItemBarPropertyEnum.exBarShowPercentCaption,true); var_Bar.set_Def(EXG2ANTTLib.ItemBarPropertyEnum.exBarPercent,1); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Left"); var_Items.AddBar(h,"Percent",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarAlignPercentCaption,0); h = var_Items.AddItem("Center"); var_Items.AddBar(h,"Percent",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarAlignPercentCaption,1); h = var_Items.AddItem("Right"); var_Items.AddBar(h,"Percent",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarAlignPercentCaption,2); h = var_Items.AddItem("Left"); var_Items.AddBar(h,"Percent",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarAlignPercentCaption,0); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarPercent,0.5); h = var_Items.AddItem("Center"); var_Items.AddBar(h,"Percent",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarPercent,0.5); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarAlignPercentCaption,1); h = var_Items.AddItem("Right"); var_Items.AddBar(h,"Percent",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarAlignPercentCaption,2); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarPercent,0.5); axG2antt1.EndUpdate(); |
649 |
Is there any way to change the format of the percent being displayed on the progress bar
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Chart.Bars.Add("Task%Progress").Shortcut = "Percent"; EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Percent",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarPercent,0.4); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarShowPercentCaption,true); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarPercentCaptionFormat,"<b>%p/100</b>"); |
648 |
How can I show or hide the percent value in the progress bar
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Chart.Bars.Add("Task%Progress").Shortcut = "Percent"; EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Percent",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarPercent,0.4); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarShowPercentCaption,true); |
647 |
How can I change the percent value in a progress bar
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Chart.Bars.Add("Task%Progress").Shortcut = "Percent"; EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Percent",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarPercent,0.4); |
646 |
How can I add a percent bar
// BarResize event - Occurs when a bar is moved or resized. private void axG2antt1_BarResize(object sender, AxEXG2ANTTLib._IG2anttEvents_BarResizeEvent e) { System.Diagnostics.Debug.Print( e.key.ToString() ); } //this.axG2antt1.BarResize += new AxEXG2ANTTLib._IG2anttEvents_BarResizeEventHandler(this.axG2antt1_BarResize); axG2antt1.BeginUpdate(); axG2antt1.Columns.Add("Task"); EXG2ANTTLib.Chart var_Chart = axG2antt1.Chart; var_Chart.LevelCount = 2; var_Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); var_Chart.set_PaneWidth(false,64); EXG2ANTTLib.Bar var_Bar = var_Chart.Bars.Add("Task%Progress"); var_Bar.Shortcut = "P"; var_Bar.set_Def(EXG2ANTTLib.ItemBarPropertyEnum.exBarShowPercentCaption,true); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"P",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarPercent,0.4); h = var_Items.AddItem("Task 2"); var_Items.AddBar(h,"Task%Progress",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); var_Items.set_ItemBar(h,"K2",EXG2ANTTLib.ItemBarPropertyEnum.exBarPercent,0.15); axG2antt1.EndUpdate(); |
645 |
How can I fix or lock a specified bar at runtime, in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarCanResize,false); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarCanMove,false); |
644 |
How can I enabled or disable moving a specified bar at runtime, in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarCanResize,false); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarCanMove,false); |
643 |
How can I enabled or disable sizing a specified bar at runtime, in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarCanResize,false); |
642 |
How can I change the key of the bar in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarKey,"NewK"); var_Items.set_ItemBar(h,"NewK",EXG2ANTTLib.ItemBarPropertyEnum.exBarCaption,var_Items.get_ItemBar(h,"NewK",EXG2ANTTLib.ItemBarPropertyEnum.exBarKey)); |
641 |
Can I add a bar in the chart, using your EBN files
axG2antt1.VisualAppearance.Add(1,"c:\\exontrol\\images\\normal.ebn"); axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/5/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1"," EBN "); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarBackColor,16777216); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/8/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K2",null); |
640 |
How can I change the background color of the bar in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Chart.Bars.Copy("Task","TaskR").Color = (uint)ColorTranslator.ToWin32(Color.FromArgb(255,0,0)); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"TaskR",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); |
639 |
How can I change the background color of the bar in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Chart.ShowNonworkingDates = false; EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarBackColor,8421504); |
638 |
How can I change the background color of the HTML text or caption of the bar in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarCaption,"<bgcolor=FF0000> to do </bgcolor>"); |
637 |
How can I change the foreground color of the HTML text or caption of the bar in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1","t<fgcolor=0000FF>o</fgcolor> do"); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarForeColor,16777215); |
636 |
How can I change the foreground color of the HTML text or caption of the bar in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarCaption,"<bgcolor=FF0000> to do </bgcolor>"); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarForeColor,16777215); |
635 |
How can I assign a tooltip to a bar in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarToolTip,"This is a bit of text that's displayed when the cursor hovers the bar"); |
634 |
How can I vertically align the HTML text or caption of the bar in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.set_ItemHeight(h,32); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarCaption,"<bgcolor=FF0000> to do </bgcolor>"); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarVAlignCaption,0); |
633 |
How can I align the HTML text or caption of the bar in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarCaption,"<bgcolor=FF0000> to do </bgcolor>"); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarHAlignCaption,0); |
632 |
How can I assign a text or some HTML caption to a bar in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarCaption," <bgcolor=FF0000>to do</bgcolor> "); |
631 |
How can I change the ending date of the bar in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarEnd,Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US"))); |
630 |
How can I change the starting date of the bar in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarStart,Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US"))); |
629 |
How can I change the style or the name of the bar in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarName,"Progress"); |
628 |
How can I access properties and methods of the bar in the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.set_ItemBar(h,"K1",EXG2ANTTLib.ItemBarPropertyEnum.exBarName,"Progress"); |
627 |
How can I remove all bars in the item
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.ClearBars(h); |
626 |
How can I remove a bar from the chart
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; int h = var_Items.AddItem("Task 1"); var_Items.AddBar(h,"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),"K1",null); var_Items.RemoveBar(h,"K1"); |
625 |
How can I add a bar and some text inside, in the chart area
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Task 1"),"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null," to do "); |
624 |
How can I add a bar and some text inside, in the chart area
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Task 1"),"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/6/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,"<bgcolor=FF0000> to do </bgcolor>"); |
623 |
How can I add an anchor or a hyperline in the chart area
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Task 1"),"",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/14/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,"just a <a1>link</a>"); |
622 |
How can I add some text or captions in the chart area
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Task 1"),"",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/14/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,"just a <b>caption</b>"); |
621 |
How can I add a bar in the chart area
axG2antt1.Columns.Add("Task"); axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); EXG2ANTTLib.Items var_Items = axG2antt1.Items; var_Items.AddBar(var_Items.AddItem("Task 1"),"Task",Convert.ToDateTime("1/2/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),Convert.ToDateTime("1/4/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")),null,null); |
620 |
Is there any option to put a picture or an icon to the thumb part of the scroll bar
axG2antt1.Images("gBJJgBAIDAAGAAEAAQhYAf8Pf4hh0QihCJo2AEZjQAjEZFEaIEaEEaAIAkcbk0olUrlktl0vmExmUzmk1m03nE5nU7nk9n0/oFBoVDolFo1HpFJpVLplNp1PqFRqVTq" + "lVq1XrFZrVbrldr1fsFhsVjslls1ntFptVrtltt1vuFxuVzul1u13vF5vV7vl9v1/wGBwWDwmFw2HxGJxWLxmNx0xiFdyOTh8Tf9ZymXx+QytcyNgz8r0OblWjyWds+m" + "0ka1Vf1ta1+r1mos2xrG2xeZ0+a0W0qOx3GO4NV3WeyvD2XJ5XL5nN51aiw+lfSj0gkUkAEllHanHI5j/cHg8EZf7w8vl8j4f/qfEZeB09/vjLAB30+kZQAP/P5/H6/y" + "NAOAEAwCjMBwFAEDwJBMDwLBYAP2/8Hv8/gAGAD8LQs9w/nhDY/oygIA="); axG2antt1.set_ScrollPartCaption(EXG2ANTTLib.ScrollBarEnum.exHChartScroll,EXG2ANTTLib.ScrollPartEnum.exThumbPart,"<img>1</img>"); axG2antt1.set_ScrollThumbSize(EXG2ANTTLib.ScrollBarEnum.exHChartScroll,24); |
619 |
How can I scroll fast the chart, or page by page
axG2antt1.Images("gBJJgBAIDAAGAAEAAQhYAf8Pf4hh0QihCJo2AEZjQAjEZFEaIEaEEaAIAkcbk0olUrlktl0vmExmUzmk1m03nE5nU7nk9n0/oFBoVDolFo1HpFJpVLplNp1PqFRqVTq" + "lVq1XrFZrVbrldr1fsFhsVjslls1ntFptVrtltt1vuFxuVzul1u13vF5vV7vl9v1/wGBwWDwmFw2HxGJxWLxmNx0xiFdyOTh8Tf9ZymXx+QytcyNgz8r0OblWjyWds+m" + "0ka1Vf1ta1+r1mos2xrG2xeZ0+a0W0qOx3GO4NV3WeyvD2XJ5XL5nN51aiw+lfSj0gkUkAEllHanHI5j/cHg8EZf7w8vl8j4f/qfEZeB09/vjLAB30+kZQAP/P5/H6/y" + "NAOAEAwCjMBwFAEDwJBMDwLBYAP2/8Hv8/gAGAD8LQs9w/nhDY/oygIA="); axG2antt1.ScrollHeight = 20; axG2antt1.ScrollButtonWidth = 20; axG2antt1.AllowChartScrollPage = true; axG2antt1.set_ScrollPartCaption(EXG2ANTTLib.ScrollBarEnum.exHChartScroll,EXG2ANTTLib.ScrollPartEnum.exLeftB5Part,"<img>1</img>"); axG2antt1.set_ScrollPartCaption(EXG2ANTTLib.ScrollBarEnum.exHChartScroll,EXG2ANTTLib.ScrollPartEnum.exRightB1Part,"<img>2</img>"); |
618 |
How can I scroll fast the chart, or page by page
axG2antt1.ScrollButtonWidth = 16; axG2antt1.AllowChartScrollPage = true; axG2antt1.set_ScrollPartCaption(EXG2ANTTLib.ScrollBarEnum.exHChartScroll,EXG2ANTTLib.ScrollPartEnum.exLeftB5Part,"<<"); axG2antt1.set_ScrollPartCaption(EXG2ANTTLib.ScrollBarEnum.exHChartScroll,EXG2ANTTLib.ScrollPartEnum.exRightB1Part,">>"); |
617 |
How can I scroll fast the chart, or page by page
|
616 |
How can I display years, from 3 to 3
axG2antt1.Chart.UnitWidth = 64; EXG2ANTTLib.Level var_Level = axG2antt1.Chart.get_Level(0); var_Level.Label = "<%yyyy%>"; var_Level.Unit = EXG2ANTTLib.UnitEnum.exYear; var_Level.Count = 3; |
615 |
How can I display years
axG2antt1.Chart.UnitWidth = 64; EXG2ANTTLib.Level var_Level = axG2antt1.Chart.get_Level(0); var_Level.Label = "<%yy%>"; var_Level.Unit = EXG2ANTTLib.UnitEnum.exYear; |
614 |
How can I display years
|
613 |
How can I display months, from 3 to 3
axG2antt1.Chart.FirstVisibleDate = Convert.ToDateTime("1/1/2001",System.Globalization.CultureInfo.GetCultureInfo("en-US")); axG2antt1.Chart.LevelCount = 2; axG2antt1.Chart.UnitWidth = 64; axG2antt1.Chart.get_Level(0).Label = 1; EXG2ANTTLib.Level var_Level = axG2antt1.Chart.get_Level(1); var_Level.Label = "<%mmmm%>"; var_Level.Unit = EXG2ANTTLib.UnitEnum.exMonth; var_Level.Count = 3; |
612 |
How can I display months
axG2antt1.Chart.UnitWidth = 64; axG2antt1.Chart.LevelCount = 2; axG2antt1.Chart.get_Level(0).Label = 1; EXG2ANTTLib.Level var_Level = axG2antt1.Chart.get_Level(1); var_Level.Label = "<%mmmm%>/<%yy%>"; var_Level.Unit = EXG2ANTTLib.UnitEnum.exMonth; |
611 |
How can I display months
axG2antt1.Chart.LevelCount = 2; axG2antt1.Chart.UnitWidth = 64; axG2antt1.Chart.get_Level(0).Label = 1; axG2antt1.Chart.get_Level(1).Label = 16; |
610 |
How can I display weeks
axG2antt1.Chart.LevelCount = 2; axG2antt1.Chart.UnitWidth = 64; axG2antt1.Chart.get_Level(0).Label = 17; axG2antt1.Chart.get_Level(1).Label = 256; |
609 |
How can I display weeks
axG2antt1.Chart.LevelCount = 2; axG2antt1.Chart.get_Level(0).Label = 17; axG2antt1.Chart.get_Level(1).Label = "<%ww%>"; |
608 |
How can I display days, from 2 to 2
axG2antt1.Chart.LevelCount = 2; axG2antt1.Chart.get_Level(0).Label = 256; EXG2ANTTLib.Level var_Level = axG2antt1.Chart.get_Level(1); var_Level.Label = "<%dd%>"; var_Level.Count = 2; |
607 |
How can I display days
axG2antt1.Chart.LevelCount = 2; axG2antt1.Chart.get_Level(0).Label = 256; axG2antt1.Chart.get_Level(1).Label = "<%dd%>"; |
606 |
How can I display days
axG2antt1.Chart.LevelCount = 2; axG2antt1.Chart.get_Level(0).Label = 256; axG2antt1.Chart.get_Level(1).Label = 4096; |
605 |
How can I display hours, from 6 to 6
axG2antt1.Chart.FirstVisibleDate = "00:00"; axG2antt1.Chart.LevelCount = 2; axG2antt1.Chart.get_Level(0).Label = 4096; EXG2ANTTLib.Level var_Level = axG2antt1.Chart.get_Level(1); var_Level.Label = "<%hh%>"; var_Level.Count = 6; |
604 |
How can I display hours
axG2antt1.Chart.LevelCount = 2; axG2antt1.Chart.get_Level(0).Label = 4096; axG2antt1.Chart.get_Level(1).Label = "<%hh%>"; |
603 |
How can I display hours
axG2antt1.Chart.LevelCount = 2; axG2antt1.Chart.get_Level(0).Label = 4096; axG2antt1.Chart.get_Level(1).Label = 65536; |
602 |
How can I display minutes, from 15 to 15
axG2antt1.Chart.FirstVisibleDate = "00:00"; axG2antt1.Chart.LevelCount = 2; axG2antt1.Chart.get_Level(0).Label = 65536; EXG2ANTTLib.Level var_Level = axG2antt1.Chart.get_Level(1); var_Level.Label = "<%nn%>"; var_Level.Count = 15; |
601 |
How can I display minutes
axG2antt1.Chart.LevelCount = 2; axG2antt1.Chart.get_Level(0).Label = 65536; axG2antt1.Chart.get_Level(1).Label = "<%nn%>"; |